Category
Electrical
Status
Delivered
Coverage Area
Wide Presence
Timeline
7 – 9 Months
— Scope of Work
Electrical Power Distribution
- CCTV & access control system installation.
- FM200 fire alarm & suppression setup.
- Linear Technology monitoring integration.
- EMT & PVC conduit installation.
- Power & data cable pulling and termination.
- Cable tray installation & management.
- AC & DC cable pulling for distribution.
- Cable labeling, dressing & testing.
- Electrical termination, testing & commissioning.
- Structured tray networks for efficiency.
— Technology
Technologies and Tools We Use
- CCTV & Access Control
IP Cameras, NVRs, Access Points, PoE Switches - Fire Suppression System (FM-200)
Alarm panels, gas suppression units, safety compliance - Cable Infrastructure & Termination
EMT & PVC conduits, AC/DC cable pulling, labeling & testing - Cable Tray & Panel Board Installation
Cable trays, MDB, ATS, EMDB, Panel boards - Tools & Software
Fluke testers, crimpers, AutoCAD, ETAP, Excel - Top Brands Used
ABB, Schneider, Honeywell, Bosch, Cisco